Tata Battery Plant Loses Second Builder in Five Months as UK EV Strategy Falters

Tata-owned Agratas' £5.2bn Somerset battery gigafactory has lost its second lead contractor in five months, raising fresh doubts about UK EV battery manufacturing capacity and timelines for production.

By The UK Pulse Editorial Team·Source: The Guardian··5 min read·How we work
The Freelander electric SUV is displayed at a launch event as people photograph it

A major British electric vehicle battery manufacturing project has descended into fresh crisis after its second lead construction contractor departed in five months, intensifying concerns about the UK's ability to establish a domestic battery supply chain for its automotive sector.

The £5.2 billion gigafactory in Bridgwater, Somerset, is being developed by Agratas, a subsidiary of Indian conglomerate Tata Group, to manufacture batteries for Jaguar Land Rover, Britain's largest automotive employer and a sister company within the same group. According to The Guardian, construction specialist TSL, formally known as Tonroe Group, has withdrawn from the project after failing to reach agreement with Agratas on project terms.

The departure marks the second major contractor exit since the project's inception. Sir Robert McAlpine, the initial lead contractor, previously departed the scheme. Construction Enquirer reported that Agratas and Sir Robert McAlpine mutually agreed to part ways after completing the project's first phase, with the contractor supporting an orderly handover.

The government has backed the Somerset facility because it is viewed as essential to the long-term viability of the British car manufacturing industry. Controls Drives Automation reported that the government announced a £380 million grant for the project in April 2026. However, the construction programme has experienced multiple delays and setbacks that have raised questions about whether the facility can meet its production targets.

Battery manufacturing represents one of the most critical components of electric vehicle production, yet global supply chains remain heavily concentrated in China, South Korea and Japan. Both Conservative and Labour governments have prioritised developing a British battery supply chain as part of broader efforts to strengthen domestic automotive manufacturing. The government subsidy has not been fully disbursed, with payments contingent on project milestones.

Why has the second contractor left?

Disagreements over project timeline and cost drove the breakdown between Agratas and TSL, according to sources familiar with the negotiations. The disputes mirror tensions that characterised the earlier separation from Sir Robert McAlpine, with discussions over the terms of that departure reportedly still ongoing.

TSL is expected to depart the site within two to three months, leaving no primary construction contractor currently engaged. However, NG Bailey, which serves as the project's mechanical, electrical and plumbing contractor, has been identified as a potential candidate to assume responsibility for the entire build.

What impact will this have on production timelines?

Agratas initially targeted 2026 for production commencement with an anticipated workforce of 4,200 employees, before revising that to 2027. The company subsequently announced a target of January 2028 for production launch. The loss of a second lead contractor in five months is likely to further jeopardise this latest timeline, though Agratas has not yet formally announced another delay.

Ad (425x293)

A spokesperson for Agratas stated:

We are on track to meet our customer requirements. The Somerset site is a large and complex industrialisation project, and all of our supplier partners are supporting us well as we prepare for the facility's launch phase.

The shell structure of the Somerset facility is substantially complete. National Grid has commenced work on the electricity substation required to supply the substantial power demands of battery manufacturing operations. Agratas has stated that the site is expected to support approximately 7,500 supply-chain jobs during construction, with projections of more than £700 million in annual economic value for the South West region at full capacity.

How are staffing challenges affecting the project?

Morale within Agratas has been damaged by the company's decision to relocate certain workers from Coventry, where they occupied space in a building shared with other Tata Group companies, to Somerset. A number of those employees are expected to accept redundancy rather than relocate their families across 120 miles. Such departures would extend a pattern of senior staff leaving the organisation in recent months, according to sources close to the business.

Some Agratas managers travelled to India this week to exchange experiences with counterparts at the company's parallel facility in Sanand, western India, and to discuss the UK project's current situation.

What is the broader context for UK battery manufacturing?

The UK's only currently operational gigafactory, AESC's facility in Sunderland in north-east England, has also encountered difficulties as vehicle manufacturers have reduced their electric vehicle production forecasts in response to government delays in implementing bans on petrol and diesel cars. The Guardian previously reported that AESC failed to secure a separate supply agreement with Jaguar Land Rover.

Jaguar Land Rover has secured battery supplies from alternative sources, meaning the company's plans to expand electric vehicle sales will not be compromised. However, the initial vehicles produced will not incorporate British-manufactured batteries, though the manufacturer could potentially qualify for incentives if it uses batteries manufactured in Europe.

The challenges facing Agratas stand in contrast to earlier optimism about UK battery manufacturing capacity. According to ACE Net, the project's steel frame was completed through delivery by Sir Robert McAlpine, steel contractor Severfield and engineering team Stantec, in an April 2026 report demonstrating initial construction progress.

Industry observers suggest that Agratas may still achieve success in producing batteries and avoid the fate of an earlier competitor. The former Britishvolt site in north-east England, which faced its own financial difficulties, is now being converted into a datacentre for artificial intelligence—a potentially valuable alternative use for a vacant building with high-capacity electricity grid connections.

What happens next for the project?

Agratas indicated it would transition to a new construction partner for the subsequent phase of development. However, the company has not yet publicly identified a replacement contractor, leaving uncertainty about the project's immediate future and its ability to meet the January 2028 production target.