Court Set to Quash Permission for Ditcher Law Wind Farm in Scottish Borders

Scottish Borders Council's legal challenge may block an eight-turbine wind farm at Ditcher Law after the government granted permission despite local objections.

·3 min read
PA Media A wind turbine with thistles in the foreground

Legal Challenge Threatens Wind Farm Plans in Scottish Borders

Plans to construct a wind farm comprising eight turbines, each reaching up to 200 meters (656 feet) tall at Ditcher Law near Lauder, are facing cancellation following a legal challenge by the local council against a Scottish government decision.

In February, the Energy Consents Unit (ECU) of the Scottish government granted planning permission for the project, despite objections from the Scottish Borders Council (SBC) concerning the potential negative effects on local residents and the surrounding landscape.

LDRS A grassy hill, with some trees and hedges in the background. The sky is blue with a few scattered clouds. There is what looks like a large greenhouse in the middle of the picture.
Developers wanted to erect eight wind turbines at Ditcher Law

After preliminary court hearings, the government has decided not to contest the legal challenge. A joint motion to have the planning permission quashed is currently before the Court of Session.

Council's Role and Timeline of Events

The planning application for the Ditcher Law wind farm was submitted in September 2023. Due to the scale of the project, the ECU led the application process, with SBC acting as a statutory consultee.

However, the developer, Ditcher Law Ltd, delayed submitting key documentation, including an impact study, until April 2024—just five weeks before the ECU's deadline.

Advertisement

Despite the council's notification that it could not review the additional information for several months due to a backlog of renewable energy applications, its request for an extension of the deadline was denied.

Council Opposition and Legal Proceedings

In September, SBC's planning committee voted to oppose the development, citing that the impact of connecting the wind farm to the electricity grid through a designated Special Landscape Area had not been adequately assessed.

Earlier in 2024, the ECU ruled that the council's concerns were raised too late in the application process and proceeded to grant permission to Ditcher Law Ltd. This decision prompted the council to initiate a legal challenge at the Court of Session.

SBC A man with dark hair, wearing a dark jacket, white shirt and yellow tie looks at the camera
Former council leader David Parker represents the area around Lauder

Local councillor David Parker commented on the situation:

"It was important that we took action and we have been successful in ensuring this wind farm has its consent quashed."
"It is important to recognize, with so many renewable energy projects that people are concerned about, that if the government does not follow due process the council will stand up for the community's concerns and take action."

Current Status and Responses

The joint motion to quash the planning permission remains under consideration by the Court of Session. The Scottish government has stated that it would not be appropriate to comment at this stage.

Attempts to obtain comments from the developer, Ditcher Law Ltd, have been made but no response has been reported.